Project Management: Achieving Competitive Advantage
Fifth Edition
Chapter 9
Project Scheduling: Networks, Duration Estimation, and Critical Path
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
If this PowerPoint presentation contains mathematical equations, you may need to check that your computer has the following installed:
1) MathType Plugin
2) Math Player (free versions available)
3) NVDA Reader (free versions available)
1
Learning Objectives (1 of 2)
9.1 Understand the importance of project scheduling techniques.
9.2 Understand and apply key scheduling terminology.
9.3 Develop an activity network using Activity-on-Node (A O N) technique.
9.4 Perform activity duration estimation based on the use of probabilistic estimating techniques.
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Learning Objectives (2 of 2)
9.5 Construct the critical path for a project schedule network using forward and backward passes, determine project slack, and calculate the probability of finishing on time.
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
P M B o K Core Concepts
Project Management Body of Knowledge (P M B o K) covered in this chapter includes:
Plan Schedule Management (P M B o K 6.1)
Define Activities (P M B o K 6.2)
Sequence Activities (P M B o K 6.3)
Estimate Activity Resources (P M B o K 6.4)
Estimate Activity Durations (P M B o K 6.5)
Develop Schedule (P M B o K 6.6)
Control Schedule (P M B o K 6.7)
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Project Scheduling
Project scheduling requires us to follow some carefully laid-out steps, in , for the schedule to take shape. P M B o K states, “an output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources.”
Project planning, as it relates to the scheduling process, has been defined by the P M B o K as:
The identification of the project objectives and the ed activity necessary to complete the project including the identification of resource types and quantities required to carry out each activity or task.
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Network Diagram—Serial Sequential Logic
Figure 9.2A Alternative Activity Networks for Term Paper Assignment
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Network Diagram – Nonserial Sequential Logic
Figure 9.2B Alternative Activity Networks for Term Paper Assignment
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Project Scheduling Terms (1 of 4)
Project Network Diagram: Any schematic display of the logical relationships of project activities.
Path: A sequence of activities defined by the project network logic.
Event: A point when an activity is either started or completed.
Node: One of the defining points of a network; a junction point joined to some or all of the other dependency lines (paths).
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Project Scheduling Terms (2 of 4)
Predecessors: Those activities that must be completed prior to initiation of a later activity in the network.
Successors: Activities that cannot be started until previous activities have been completed. These activities follow predecessor tasks.
Early start (E S) date: The earliest possible date the uncompleted portions of an activity can start.
Late start (L S) date: The latest possible date that an activity may begin without delaying a specified milestone.
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Project Scheduling Terms (3 of 4)
Forward pass: Network calculations to determine earliest start/earliest finish for an activity through working forward through each activity in network.
Backward pass: Network calculations to determine late start/late finish for uncompleted tasks through working backward through each activity in network.
Merge activity: An activity with two or more immediate predecessors.
Burst activity: An activity with two or more immediate successors.
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Project Scheduling Terms (4 of 4)
Float: The amount of time an activity may be delayed from its early start without delaying the finish of the project.
Critical path: The path through project network with the longest duration.
Critical Path Method: A network analysis technique used to determine the amount of schedule flexibility on logical network paths in project schedule network and to determine minimum project duration.
Resource-limited schedule: Start and finish dates reflect expected resource availability.
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
A O A Versus A O N
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Node Labels
Figure 9.3 Labels for Activity Node
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Serial Activities
Serial activities are those that flow from one to the next, in sequence.
Figure 9.5 Project Activities Linked in Series
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Concurrent Activities
When the nature of the work allows for more than one activity to be accomplished at the same time, these activities are called concurrent, and parallel project paths are constructed through the network.
Figure 9.6 Activities Linked in Parallel (Concurrent)
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Figure 9.7 Merge Activity
Activity D can only begin following the completion of activities A, B, and C.
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Figure 9.8 Burst Activity
Activities B, C, and D can only begin following the completion of activity A.
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Complete Activity Network
Figure 9.10 Complete Activity Network for Project Delta
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Duration Estimation Methods
Experience
Expert opinion
Mathematical derivation—Beta distribution
Most likely (m)
Most pessimistic (b)
Most optimistic (a)
Two assumptions used to convert m, a, and b into time estimates (T E) and variances
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Figure 9.14 Symmetrical (Normal) Distribution for Activity Duration Estimation
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Figure 9.15 Asymmetrical (Beta) Distribution for Activity Duration Estimation
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Activity Duration Estimates (1 of 2)
Table 9.2 Activity Duration Estimates for Project Delta
Name: Project Delta
Durations are listed in weeks
Activity Description Optimistic Most Likely Pessimistic
A Contract signing 3 4 11
B Questionnaire design 2 5 8
C Target market I D 3 6 9
D Survey sample 8 12 20
E Develop presentation 3 5 12
F Analyze results 2 4 7
G Demographic analysis 6 9 14
H Presentation to client 1 2 4
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
22
Activity Duration Estimates (2 of 2)
Table 9.3 Estimated Project Activity Times Using Beta Distribution
Name: Project Delta
Durations are listed in weeks
Activity Description T E start fraction left parenthesis 1:4:1 ration right parenthesis over 6
A Contract signing 5
B Questionnaire design 5
C Target market I D 6
D Survey sample 12.7
E Develop presentation 5.8
F Analyze results 4.2
G Demographic analysis 9.3
H Presentation to client 2.2
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Constructing the Critical Path
Forward pass—an additive move through the network from start to finish
Backward pass—a subtractive move through the network from finish to start
Critical path—the longest path from end to end which determines the shortest project length
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Figure 9.16 Partial Project Activity Network with Task Durations
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Figure 9.18 Activity Network with Forward Pass
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Figure 9.19 Activity Network with Backward Pass
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Figure 9.20 Project Network with Activity Slack and Critical Path
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Figure 9.24 A O N Network with Laddering Effect
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Figure 9.25 Example of a Hammock Activity
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Options for Reducing the Critical Path
Eliminate tasks on the critical path.
Replan serial paths to be in parallel.
Overlap sequential tasks.
Shorten the duration on critical path tasks.
Shorten early tasks.
Shorten longest tasks.
Shorten easiest tasks.
Shorten tasks that cost the least to speed up.
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Summary (1 of 2)
Understand the importance of project scheduling techniques.
Understand and apply key scheduling terminology.
Develop an activity network using Activity-on-Node (A O N) technique.
Perform activity duration estimation based on the use of probabilistic estimating techniques.
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Summary (2 of 2)
Construct the critical path for a project schedule network using forward and backward passes, determine project slack, and calculate the probability of finishing on time.
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Copyright
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
s
2
)
(
are:
++
==
a4
ActivityDurationTE
6
mb
–
æö
==
ç÷
èø
ba
s
2
2
ActivityVariance
6
(
)
TE 1:4:1 ratio/6
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more